24 September 2004 Manufacture of 8.4-m off-axis segments: a 1/5-scale demonstration
Hubert M. Martin, James H. Burge, Brian Cuerden, Stephen M. Miller, Bryan Smith, Chunyu Zhao
Author Affiliations +
Abstract
We describe the requirements for manufacturing and maintaining alignment of the 8.4 m off-axis segments of the Giant Magellan Telescope’s primary mirror, and a demonstration of the manufacturing techniques on the 1.7 m off-axis primary mirror of the New Solar Telescope. This mirror is approximately a 1/5 scale model of a GMT segment. We show that the stressed lap polishing system developed for highly aspheric primary and secondary mirrors is capable of figuring the GMT segments and the NST mirror. We describe an optical test with a null corrector consisting of a tilted spherical mirror and a computer-generated hologram, and derive accuracy requirements for the test. The criterion for accuracy of low-order aberrations is that the active support system can correct any figure errors due to the laboratory measurement, with acceptably small forces and residual errors.
© (2004) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Hubert M. Martin, James H. Burge, Brian Cuerden, Stephen M. Miller, Bryan Smith, and Chunyu Zhao "Manufacture of 8.4-m off-axis segments: a 1/5-scale demonstration", Proc. SPIE 5494, Optical Fabrication, Metrology, and Material Advancements for Telescopes, (24 September 2004); https://doi.org/10.1117/12.552306
Lens.org Logo
CITATIONS
Cited by 16 scholarly publications.
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Mirrors

Monochromatic aberrations

Off axis mirrors

Wavefronts

Polishing

Telescopes

Aspheric lenses

RELATED CONTENT

Primary mirror segment fabrication for CELT
Proceedings of SPIE (July 20 2000)
Fabrication and measured quality of the MMT primary mirror
Proceedings of SPIE (August 25 1998)
Optics for the 20/20 telescope
Proceedings of SPIE (January 30 2003)
Production of 8.4m segments for the Giant Magellan Telescope
Proceedings of SPIE (September 13 2012)

Back to Top