6 July 2018 The ESO's ELT construction status
Roberto Tamai, Bertrand Koehler, Michele Cirasuolo, Fabio Biancat-Marchet, Mauro Tuti, Juan Carlos Gonzáles Herrera
Author Affiliations +
Abstract
Over the last few years, the ESO’s ELT has made tremendous progress in defining and procuring the many components of one of the future world largest optical-infrared telescopes. More than two dozen large scale contracts have been placed to industry to design and manufacture several items, among them the dome, the telescope structure, the mirrors and their supports, the control system, the infrastructure, and more. In addition, four agreements were signed with consortia of astronomical research institutes to develop the first suite of scientific instruments. As of today, this represents a financial commitment of more than 90% of the total ESO material budget for the ELT.
Conference Presentation
© (2018) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Roberto Tamai, Bertrand Koehler, Michele Cirasuolo, Fabio Biancat-Marchet, Mauro Tuti, and Juan Carlos Gonzáles Herrera "The ESO's ELT construction status", Proc. SPIE 10700, Ground-based and Airborne Telescopes VII, 1070014 (6 July 2018); https://doi.org/10.1117/12.2309515
Lens.org Logo
CITATIONS
Cited by 6 scholarly publications.
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Telescopes

Mirrors

Control systems

Polishing

Sensors

Optical instrument design

Coating

RELATED CONTENT


Back to Top